| The bridge is supported on tubular steel piles, approximately
80 metres in length, driven into the river bed.
Sand was removed from within the piles by airlifting and replaced with mass concrete. Out of the 50 piers, 21 piers are supported on groups of 3 piles (each of 2.5 m diameter) and 29 piers on groups of 2 piles (each of 3.15 diameter). The driving of 121 piles started on 15 October, 1995 and was completed in July 1996. The pier stems are founded on concrete pilecaps, whose shells were precast and infilled with in-situ reinforced concrete. The reinforced concrete pier stems support pierheads which contain bearings and seismic devices. These allow movement of the deck under normal loading conditions but lock in the event of an earthquake to limit overall seismic loads through the structure and minimise damage. |
Completed pilecaps stretch across the Jamuna |

| The main bridge deck is a multi-span precast prestressed
concrete segmental structure, constructed by the balanced cantilever method.
Each cantilever has 12 segments (each 4 m long), joined to a pierhead unit (2 m long) at each pier and by an in-situ stitch at mid span. The deck is internally prestressed and of single box section. The depth of the box varies between 6.5 metres at the piers to 3.25 metres at mid-span. An expansion joint is provided every 7 spans by means of a hinge segment at approximately quarter span. The segments were precast and erected using a two-span erection gantry. . |
Segment erection in process |
If you have any questions or would like some more information, send us an email